Bank Cement Ceramics Sector Corporate Bond Engineering Financial Institutions Food & Allied Fuel & Power IT Sector Insurance Jute Life Insurance Miscellaneous Mutual Funds Paper & Printing Pharmaceuticals & Chemicals Services & Real Estate Tannery Industries Telecommunication Textile Travel & Leisure All
  • Details
  • Chart
  • News

DOREENPWR

All Eps Dividend Board Agm Q1 Q2 Q3

DOREENPWR 23-Oct-2016

(Continuation news of DOREENPWR): The Company has also reported consolidated EPS of Tk. 0.64, consolidated NAV per share (with revaluation) of Tk. 34.34, consolidated NAV per share (without revaluation) of Tk. 24.67 and consolidated NOCFPS of Tk. 1.13 for the year ended on 30.06.2016 as against Tk. 2.25, Tk. 36.00, Tk. 22.30 and Tk. 5.90 respectively for the year ended on 30.06. 2015. (end)

DOREENPWR 23-Oct-2016

The Board of Directors has recommended 10% cash dividend for all shareholders excluding the Sponsors/Directors and 20% stock dividend for all shareholders for the year ended on June 30, 2016. The Sponsors/Directors hold 60 million shares and the cash dividend to be payable to the General shareholders is Tk. 20.00 million. Date of AGM: 18.12.2016, Time: 10:30 AM, Venue: Trust Milonayaton, 545 old Air Port Road, Dhaka Cantonment, Dhaka-1206. Record Date: 13.11.2016. (cont.)

DOREENPWR 13-Oct-2016

As per Regulation 16(1) of the Dhaka Stock Exchange (Listing) Regulations, 2015, the Company has informed that a meeting of the Board of Directors will be held on October 22, 2016 at 3:00 PM to consider, among others, un-audited financial statements of the Company for the Third Quarter (Q3) period ended on September 30, 2016.

DOREENPWR 13-Oct-2016

As per Regulation 19(1) of the Dhaka Stock Exchange (Listing) Regulations, 2015, the Company has informed that a meeting of the Board of Directors will be held on October 22, 2016 at 3:00 PM to consider, among others, audited financial statements of the Company for the year ended on June 30, 2016.

DOREENPWR 29-Sep-2016

(continuation news of DOREENPWR): As per Power Purchase Agreement, BPDB will purchase the power from the plant for 15 years from the date of COD. Dhaka Northern Power Generations Limited will generate approximately Tk. 313.74 crore as revenue per year. As 98.52% shareholding owner, Doreen Power Generations and Systems Limited will be benefited from the above mentioned revenue proportionality. (end)

DOREENPWR 29-Sep-2016

The Company has informed that Bangladesh power Development Board (BPDB) has approved the Commercial Operation (COD) of 55MW Power Plant at Manikganj of Dhaka Northern Power Generations Limited with effect from 17.08.2016. The plant has been successfully completed the COD procedure with its full (100%) dependable capacity of 55MW. (cont.)

DOREENPWR 11-Aug-2016

The Company has informed that the Board of Directors of the Company has decided to purchase 13 decimals land at total cost of Tk. 38,98,200.00 only (approximately) including the Registration cost at Shorshodi, Devipur, Feni Sadar, Feni (adjacent to the existing Feni 22MW Power Plant of the Company).

DOREENPWR 11-Jul-2016

With reference to their earlier news (disseminated by DSE on 28.06.2016), the Company has further informed that Bangladesh power Development Board (BPDB) has approved the Commercial Operation (COD) of 55MW Power Plant at Nobabganj, Dhaka of Dhaka Southern Power Generations Limited with effect from 17.06.2016. The plant has been successfully completed the COD procedure with its full (100%) dependable capacity of 55MW.

DOREENPWR 28-Jun-2016

With reference to their earlier news (disseminated by DSE on 19.06.2016), the Company has further informed that Dhaka Southern Power Generations Limited, a subsidiary of Doreen Power Generations and Systems Limited, will generate Tk. 313.74 crore (approx.) as revenue per year at a plant factor of 80% capacity after completion of the COD of 55 MW Power Plan. As a 96.78% shareholder, Doreen Power Generations and Systems Limited will be benefited from the above mentioned revenue proportionately.

DOREENPWR 19-Jun-2016

The Company has informed that Dhaka Southern Power Generations Limited, a subsidiary of Doreen Power Generations and Systems Limited which holds 96.78% shares, has successfully completed COD procedure of 55MW Power Plant at Nababganj, Dhaka. The commercial operation date of the Plant was on June 17, 2016, subject to the approval of Bangladesh Power Development Board.